== Summary==
 
== Summary==
 
One paragraph summary which summarises the main ideas of the article.
 
One paragraph summary which summarises the main ideas of the article.
 
== Description ==
 
The following processes and tools can be used by [[Nuclear power plants|nuclear power plants]] to
 
identify and mitigate [[Knowledge loss|knowledge loss]] threats. Management can adapt or modify
 
these processes and tools to meet the specific needs of their organization.
 
 
=== Attrition related knowledge loss risk assessment ===
 
[[Attrition]] related knowledge loss threats can be identified, prioritized and
 
addressed using the following process to determine a total risk factor for each
 
employee in the organization. This total risk factor is based on a projected
 
attrition date, which could be retirement, transfer, or other attrition (attrition
 
risk factor), and criticality of knowledge and skill (position risk factor). This
 
three step process has been succesfully implemented by the Tennessee Valley
 
Authority (TVA) in the USA. Figure 1 is a flow diagram of the critical
 
knowledge retention process. Knowledge retention roles and responsibilities
 
are outlined in Annex I.
 
 
[[File:Critical-knowledge-flow.PNG|thumb|right|500px|Fig 1. Critical knowledge retention flow chart]]
 
 
=== The three step process ===
 
 
==== Step 1 Conduct of a knowledge loss risk assessment ====
 
Conduct of a [[Knowledge loss risk assessment|knowledge loss risk assessment]]
 
The knowledge loss risk assessment is designed to identify positions/
 
individuals where the potential for knowledge loss is greatest and most
 
imminent.
 
 
The attrition risk factor is based on the expected retirement or other
 
attrition date. The date can be provided by the employee or calculated
 
according to age and tenure data. Table 1 lists the criteria used to assign an
 
attrition risk factor.
 
 
The position risk factor is initially assigned by the department level
 
manager using criteria listed in Table 2. The position risk factor criteria are
 
based on the unique/critical knowledge and skills possessed by the employee
 
and an estimate of the difficulty or level of effort required to refill the position.
 
In assigning the factor the manager should consider each employee’s responsibilities
 
and background, formal and informal roles, collateral duties, recurrent
 
assignments (e.g. outage related duties, problem solving or trouble shooting
 
assignments) and other factors suggesting that the employee may have unique/
 
critical knowledge and skills. Department managers may want to consult other
 
work group members, key plant customers, or interested parties when
 
determining ratings.
 
 
The total risk factor of an employee is determined on the basis of the
 
guidelines provided in Table 3. The total risk factor provides an overall
 
assessment of attrition related risk for knowledge loss. The total risk factor is
 
computed by multiplying the attrition risk factor by the position risk factor (see
 
Table 4).
 
 
Each nuclear power plant management team should collectively review of
 
the results of the risk assessment. Experience has shown that a critical review of the position risk factor assigned by the department manager is important in
 
ensuring accurate ratings. Often there is a tendency to rate high performing
 
employees as having unique and critical knowledge and skills. A high level of
 
performance is not the basis for a high position risk factor (5 rating) and such
 
ratings should be changed. After completing the collective review, the
 
management team identifies where a knowledge retention plan is needed and
 
assigns responsibility for plan development (typically, to the employee’s
 
supervisor or manager).
 
 
==== Capture of critical knowledge|Step 2 Determination of the approach needed to capture critical knowledge====
 
Once the risk assessment is complete, the next step is to address the
 
potential [[Knowledge loss|knowledge loss]] for each high priority (20–25 total risk factor)
 
employee. In many cases this will involve an [[Interview|interview]] with the employee (the
 
elicitation process) utilizing a trained elicitor. The knowledge and skills in
 
question may be of many different types — task and equipment related
 
knowledge and skills; facts or information about specific people, vendors,
 
projects and locations; and unique pattern recognition knowledge and problem
 
solving skills. The interviews employ questionnaires designed to assist the
 
elicitor and employee in identifying the specific areas where critical/unique
 
knowledge may exist. Guidelines for conducting interviews and suggested
 
questions are contained in Annex II.
 
 
On the basis of the results of the interviews, knowledge retention plans
 
(Annexes III and IV) are developed and implemented. The process for
 
determining and implementing the most appropriate method(s) for addressing
 
this potential loss involves:
 
 
* Inventory of the specific knowledge and skills of the identified employee;
 
* Assessment of the importance to the organization (criticality);
 
* Assessment the consequences of loss (e.g. operational, financial);
 
* Review of the mitigation options (e.g. codification, alternative resources, re-engineering);
 
* Development of knowledge retention plans as needed;
 
* Implementation of knowledge retention plans;
 
* Coordination and review of knowledge retention plans.
 
 
The first priority is to [[Identification|identify]], [[Capture|capture]] and [[Retention|retain]] [[Critical knowledge|critical knowledge]] held
 
by employees nearing retirement. However, it is also important to develop and
 
implement a [[Retention plan|knowledge retention plan]] for any employee with a position risk
 
factor of five. These employees may be promoted, transferred, or may leave the
 
organization for other reasons, resulting in the loss of critical knowledge.
 
 
==== Step 3 Monitoring and evaluation ====
 
 
Periodic reviews should be conducted to monitor the status of implementation
 
of the knowledge retention process. Specifically, this step should:
 
 
* Review previous knowledge retention plans and progress.
 
* Identify any positions/incumbents requiring reassessment or knowledge retention plan development.
 
* Identify related emerging issues or points of coordination.
 
* Review knowledge retention metrics, including:
 
** Future attrition projections;
 
** Number of high priority positions;
 
** Number of positions targeted for knowledge retention plan development;
 
** Status of knowledge retention plans (complete, on-track, etc.);
 
** Knowledge related organization metrics (human performance, safety, etc.);
 
** Consideration of the impact of other activities on the risk assessment (e.g. emerging work).
 
* Evaluate the success of knowledge retention plans in accomplishing stated goals.
 
 
Additional information about the TVA knowledge retention process is
 
available on the TVA web site: http://www.tva.gov/knowledgeretention/
 
 
=== Employee self-assessment–knowledge retention process ===
 
 
Often the expert employee who has undocumented knowledge is critical
 
to day-to-day operations of the plant and therefore their time is valuable and
 
limited. Processes such as the one outlined in Section 3.1 are effective, but may
 
require significant resources and time. The following process (detailed in
 
Annex V) can be much less time consuming when utilized by nuclear power
 
plants to allow for self-assessments in order to identify specific ‘at risk’
 
knowledge. This approach can be used to address potential knowledge loss
 
when employees are being terminated, transferred, promoted, etc. The process
 
can facilitate the gathering of additional information pertinent to the
 
individual’s knowledge, skills and duties to support the continued safe and
 
efficient operation of the plant.
 
 
The self-assessment consists of two steps — the employee self-assessment
 
and the employee task assessment. The employee self-assessment is geared to
 
obtaining general information from the employee on their current job tasks as
 
well as information regarding meetings they attend, emergency positions they
 
hold, etc. The employee task assessment provides more specific information
 
about 1–5 major tasks performed by the employee. These major tasks may
 
include activities they perform as part of their everyday job or they may be
 
collateral duties such as outage assignments.
 
 
The critical knowledge held can either be apparent, where the individual
 
is recognized as ‘the’ expert in a task or area, or it may be deep seated, where
 
critical steps are so ingrained in the individual that they may or may not
 
recognize them as critical. This method of knowledge retention is a selfelicitation
 
method that may need to be followed up with a more detailed review
 
of the employee’s information (e.g. the process outlined in Section 3.1.1.2).
 
 
Once the employee has completed both the employee self-assessment
 
and the employee task assessment, department managers and supervisors
 
should review the tasks performed by the individual and make a decision as to
 
whether additional assessments are needed. The completed self-assessment is
 
retained by the manager and is used to address challenges created by the
 
pending personnel changes as well as the potential knowledge loss.
 
 
=== Risk management of institutional knowledge loss ===
 
 
[[Institutional knowledge]] is defined as the collective knowledge of all the
 
employees working in an organization or institution. Sections 3.1 and 3.2
 
provide processes and tools to address specific knowledge loss associated with
 
individual expert workers nearing retirement or employees transferring,
 
receiving promotions or leaving the organization (or industry) for other
 
reasons. This section will consider the impact of knowledge loss on the organization
 
and the resulting impact on organizational competency, in other words,
 
the ability to function safely and efficiently.
 
 
The necessity to maintain [[Organizational competency|organizational competency]] for nuclear power
 
plants has been widely recognized by Member States, given the nature of the
 
business (high hazard low risk) and the life cycle of 100 years or more. They
 
recognize the importance of continuing the safe and efficient operation of
 
existing facilities, supporting research and development and educational institutions,
 
and supporting the expansion of nuclear power.
 
 
The three examples of China, Germany and the USA (covered in Section
 
1.1) demonstrate that different situations or life cycle stages exist that may
 
contribute to the potential loss of knowledge and skill in the nuclear industry.
 
However, all three share the common challenge of managing nuclear
 
knowledge to maintain and enhance institutional knowledge.
 
 
As with specific knowledge loss threats, addressed in Sections 3.1 and 3.2,
 
organizations should periodically assess the risk of institutional knowledge loss.
 
This assessment should consider both internal (e.g. loss of experienced
 
workers) and external (business and political) factors. Other considerations
 
include:
 
 
# '''Current work load:''' Provision of an assessment of the current workload in the organization or department. Consideration of current work backlogs, amount of overtime (paid and unpaid) and levels of stress in the workforce. Identification of core and non-core functions performed and the impact of non-performance. Identification of options to address any potential knowledge loss issues (e.g. process improvements, reorganization and elimination of non-core activities).
 
# '''Future work load''': Evaluation of future staffing needs based on an assessment of future workload (expanded capacity, ecommissioning, restart, major modifications, etc.). Consideration of lag time in recruitment, training and time until full competency is achieved.
 
# '''Areas where critical knowledge and skills are at risk''': On the basis of current information, identification of any areas that exist where critical knowledge and skills are at risk of being lost to the organization. These areas may be general areas (e.g. system engineering) or specific to individual experts (turbine specialist). Each area or individual should be listed and details of what is at risk included. The cause of the threat should be included (e.g. retirement, transfer).
 
# Risk and impact: On the basis of workload assessments, an evaluation should be made of the risk that exists and its likely impact on organizational performance. Consideration should be given regarding what work can proceed and what will be deferred. Where possible, the impact on safety, performance and cost should be quanitified.
 
# Current programmes or proposed initiatives that support knowledge management: Recognition of existing programmes and processes and their contribution to the retention and enhancement of institutional knowledge. These may include corrective action programmes, configuration control processes, or change management tools. It is important to be as specific as possible and to identify gaps where programmes or processes need to be improved.
 
 
On the basis of the assessment results, a strategic plan to address institutional
 
knowledge loss should be developed (see Section 2).
 
 
'''Source:''' [[Risk Management of Knowledge Loss in Nuclear Industry Organizations ]]
 
  
 
==Description==
 
==Description==

Revision as of 23:39, 29 December 2013

Template:Vitalii

David.png
Tidy1.png
1 Clustering stage banner.jpg,

Priority.png,

Template:Links

Definition

Knowledge loss risk assessment in NPP's is Determining the potential business impact of the loss of critical knowledge from a nuclear organization Source: [[]]

Summary

One paragraph summary which summarises the main ideas of the article.

Description

The following processes and tools can be used by NPPs to identify and mitigate knowledge loss threats. Management can adapt or modify these processes and tools to meet the specific needs of its organization. This approach is practicaly proved itself as a basic methodology of KLRM and has been adoppted by many NPPs and other nuclear related organizations over the world. The case studies of the KLRM best practicies is showen in the annexis of the publication.

Attrition related knowledge loss risk assessment

Attrition-related knowledge loss threats can be identified, prioritized and addressed using the following process to determine a ‘Total Risk Factor’ for each employee in the organization. This Total Risk Factor is based on a projected attrition date which could be retirement, transfer, or other attrition (Attrition Risk Factor) and criticality of knowledge and skills (Position Risk Factor). This three-step process has been succesfully implemented by many nuclear organizations. Figure 7 provides a flow diagram of the critical knowledge retention (KR) process. Knowledge retention roles and responsibilities are outlined in Annex I.

FIG. 7. Critical knowledge retention flow chart

Three-step process

Step 1: Conduct knowledge loss risk assessment

The knowledge loss risk assessment is designed to identify positions/individuals with the greatest and the most imminent potential of knowledge loss . The Attrition Risk Factor is based on the expected retirement or other attrition date. The date can be provided by the employee or calculated based on the age and tenure data. Table 5 lists the criteria used to assign an Attrition Risk Factor.

TABLE 5. ATTRITION RISK FACTOR CRITERIA

The Competency Risk Factor is initially assigned by the department level manager using criteria listed in Table 6.

TABLE 6. POSITION RISK FACTOR CRITERIA

The Competency Risk Factor criteria are based on the unique/critical knowledge and skills posessed by the employee and an estimate of the difficulty or level of effort required to refill the position. In assigning the factor the manager should consider each employee’s responsibilities and background, formal and informal roles, collateral duties, re-occurring assignments (e.g., outage-related duties, problem-solving or trouble-shooting assignments), and other factors suggesting that the employee may have unique/critical knowledge and skills. Department managers may want to consult other work group members, key plant customers, or interested parties to determine ratings.

The Total Risk Factor of an employee is determined based on the guidelines provided in Table 7.

TABLE 7. TOTAL RISK FACTOR

The Total Risk Factor provides an overall assessment of attrition-related risk for knowledge loss. The Total Risk Factor is computed by multiplying the Attrition Risk Factor by the Position Risk Factor. See Table 8.

TABLE 8. EXAMPLE OF TOTAL RISK FACTOR COMPUTING

Each NPPs management team should collectively review the results of the risk assessment. Experience has shown that a critical review of the Position Risk Factor assigned by the department manager is important in ensuring accurate ratings. Often there is a tendency to rate high performing employees as having unique and critical knowledge and skills. A high level of performance is not the basis for a high Competency Risk Factor (5 rating) and such ratings should be changed. After completing the collective review, the management team identifies where a knowledge retention plan is needed and assigns responsibility for plan development (typically, the employee’s supervisor or manager).

Step 2: Determine the approach to capture critical knowledge

Once the risk assessment is complete, the next step is to address potential knowledge loss for each High Priority (20–25 Total Risk Factor) employee. In many cases this will involve an interview with the employee (‘elicitation’ process) utilizing a trained elicitor. The knowledge and skills in questions may be of many different types — task and equipment-related knowledge and skills; facts or information about specific people, vendors, projects, and locations; and unique pattern recognition knowledge and problem-solving skills. The interviews employ questionnaires are designed to assist the elicitor and employee in identifying the specific areas where critical/uinque knowledge may exist. Guidelines for conducting interviews and suggested questions are contained in Annex II. Based on the interviews’ results knowledge retention plans (see Annex III and Annex IV) are developed and implemented. The process for determining and implementing the most appropriate method(s) for addressing this potential loss involves:

  1. Inventorying specific knowledge and skills of the identified employee;
  2. Assessing the importance to the organization — criticality;
  3. Assessing the consequences of loss (e.g., operational, financial, etc.);
  4. Reviewing options to mitigate the loss (e.g., codification, alternate resources, re-engineering);
  5. Developing knowledge retention plans as necessary (see Appendix III);
  6. Implementing knowledge retention plans;
  7. Coordinating and reviewing knowledge retention plans.

The first priority is to identify, capture and retain critical knowledge held by employees nearing retirement. However, it is also important to develop and implement a knowledge retention plan for any employee with a Position Risk Factor of five. These employees may be promoted, transfered, or leave the organization for other reasons causing the loss of critical knowledge.

Employee self-assessment knowledge retention survey

Often the expert employee posesessing critical knowledge and skills is also critical to day-to-day operations of the NPP and therefore his/her time is valuable and limited. Processes such as the one outlined in para 4.2. are effective, but may require significant resources and time. The following process (detailed in Appendix V) can be much less time consuming if utilized by NPPs to allow for self-assessments to identify specific at risk knowledge. This approach should be used to address potential knowledge loss when employees are terminated, transfered, promoted, etc. The process can facilitate the gathering of additional information pertinent to the individual’s knowledge, skills and duties to support the continued safe and efficient operation of the NPP.

This activity could be a part of the performance appraisal system for already defined key experts through It-systems of the Nuclear Organizations (CMS/ERP) Review provided by peers and approved by line managers

The self-assessment consists of two steps — the Employee Self-Assessment and the Employee Task Assessment. The Employee Self-Assessment is geared to provide general information from the employees related to their current job tasks as well as information regarding meetings they attend, emergency position they hold, etc. The Employee Task Assessment provides more specific information about 1–5 major tasks performed by the employee. These major tasks may include activities they perform as part of their day-to-day job or may be collateral duties such as outage assignments. The critical knowledge can either be apparent where the individual is recognized as ‘the expert’ in a task or area, or it may be ‘deep-seated’, where critical steps are so ingrained in the individual that they may or may not recognize it as critical. This method of knowledge retention is a self-elicitation method that may need to be followed up with a more detailed review of the employee’s information (e.g., process outlined in paragraph 4.2.). Once the employee has completed both the Employee Self-Assessment and the Employee Task Assessment, department managers and supervisors should review the tasks performed by the individual and decide whether additional assessments are needed. The completed self-assessment is retained by the manager and is used to address challenges created by the pending personnel changes as well as potential knowledge loss. The instruction of (self)-assessment is detailed in the Appendix II.

Step 3: Monitor and evaluate

Periodic reviews should be conducted to monitor the status of implementation of the knowledge retention process. Specifically this step should:

  1. Review previous knowledge retention plans and progress;
  2. Identify any positions/incumbents for reassessment or knowledge retention plan development;
  3. Identify related emerging issues or points of coordination;
  4. Review knowledge retention metrics, including:
    • Future attrition projections;
    • Number of High Priority positions;
    • Number of positions targeted for knowledge retention plan development;
    • Status of knowledge retention plans (complete, on-track, etc.);
    • Knowledge-related organization metrics (human performance, safety, etc.);
    • Consideration of other activities impact on the risk assessment (e.g., emerging work).
  5. Evaluation of the knowledge retention plans success in accomplishing stated goals.

An example of the organizational aspects of the 3-steps process is described in the Appendix I. Outcomes of the evaluation process can be:

  • number of experience reports
  • number of interviews
  • ratio number of experts at risks/to experts evaluated
  • ratio number of intervied /to training material/ to tech documentations
  • number of mentoring programmes starts

Methods and tools to support knowledge loss risk management

A summary of knowledge preservation approaches covering methods and tools appropriate for each process, whether tacit, implicit, or explicit knowledge is involved, whether it exists at an individual, group/department, organizational or industry level, and whether it is focused on project, technology or process, can be found in Table 9.

TABLE 9. KNOWLEDGE PRESERVATION METHODS AND TOOLS

More detailed information on methods and tools for knowledge loss risk management is shown in IAEA Nuclear Energy Series, No. NG-T-6.7 ‘Comparative analysis of methods and tools for nuclear knowledge preservation’.

Motivational factors for knowledge transfer

Nuclear organization managers should pay attention to very important issue. How to motivate key experts with their knowledge, skills and competences to retain and transfer it to the next generation. The most common reasons for employees to stay at a company are listed below. The differences between functions, levels, genders, and ages are minor.

  1. Challenging work and diversity;
  2. Career growth, learning, and development;
  3. Working with knowledgeable people;
  4. Fair pay;
  5. Supportive management;
  6. Being recognized, valued, and respected;
  7. Benefits;
  8. Meaningful work;
  9. Pride in the organization, its mission, its culture and its product;
  10. Pleasant working and social environment;
  11. Autonomy and creativity;
  12. Flexibility: working condition, working hours, dress code;
  13. Location;
  14. Job security and stability;
  15. Being part of a friendly team;
  16. Empowerment;
  17. Organizational loyalty;
  18. Inspiring leadership.
  19. Contests and awards (best experience report)

Source: Practical Approaches to Risk Management of Knowledge Loss in Nuclear Organizations